Works are due to be completed later today but we'll monitor progress, just to be sure. Please get in touch in the usual way if you have any queries in relation to this matter:
Just following up our meeting to confirm on Tuesday April 18th we will be undertaking works to tarmac the access track.
This
will commence around 9.00am and consist of 12 no. tarmac wagons entering
Hesleden from Myra Avenue and departing along Gray Avenue. We envisage the
works will take about 4 – 5 hours.
The
wagons will reverse down the access track to deliver the materials.
The
works also include the tarmac placement on the walkway and alterations to the
walkway wooden access posts (adjacent to the barriers) by reducing the
allowable distance between posts to deter quad bikes but still allowing
wheelchair/cycle access. The tarmac on the walkway will be placed to fall to
drain into the surrounding ditches.
The
following pedestrian/traffic management will be introduced.
·
Works
in Progress signs along the access track and either side east-west along the
walkway.
·
Pedestrian
management along the walkway, if required.