I was contacted this afternoon by a resident from Dene View in High Hesleden after some vague information scrawled on a card was put through their letterbox advising that resurfacing works were scheduled to be carried out in the back lane at some point in the future.
There was no date, no time nor any additional information about the type of works to be carried out, so I contacted the service this afternoon to ask for more details. I’ve now received the following response:
Good Afternoon Cllr Crute,
I can give you more information regarding the resurfacing works happening at High Hesleden, currently I have this programmed in for Tuesday / Wednesday next week. I cannot guarantee that this will be done at this time as we do get delayed with breakdowns and cannot resurface in bad weather. Signs will be going up on site which will let residents know which days we will be laying and if we have breakdowns or bad weather the signs will be altered to keep residents updated.
I hope this has answered your query.