Hello Cllrs Pounder and Crute,
I am emailing you regarding forthcoming improvements to the
above junction.
As you’ll be aware this is currently a road safety risk at
the junction, with queueing towards the A19 from the northbound off slip. This
is caused by the flow of traffic on the A179 making it difficult for right
turners onto the A179 from the northbound off slip. This issue is particularly
evident in peak periods, with commuters travelling to and from Hartlepool. The
signalisation of the junction will remove this risk, by providing a dedicated
green light for movements from the off slip.
The signalisation of the junction will also allow certain
gaps to be closed on the central reservation of the A19, subject to Traffic
Regulation Orders led by Highways England, with accidents previously recorded
relating to right turns across the A19. The proposals will facilitate short
term housing growth in Hartlepool, in advance of a proposed new junction on the
A19 at Elwick.
Highways England have awarded £800k on Congestion Relief
funding to Durham County Council to undertake the development, design and
delivery of the project.
Subject to confirmation from the Police it is proposed
to reduce the speed limit on the A179 though the junction to 40mph, which
will safely allow right turns onto the on slips.
Subject to ongoing processes it is currently proposed to
deliver the project from August to October 2018, largely using off peak lane
closures wherever possible.
Please contact me if you have any further queries.
Regards,
03000 267103