Last week we received information from the site manager responsible for ongoing works to remove spoil from the pit heap at Hesleden. Included are details of the programmed work activity.
All comments, complaints and queries relating to this matter should be directed to:
Hesleden
Restoration Scheme
Provisional
Works Programme
Issued
18 July 2017 - V1
B
& S Recycling Ltd.,
The
provisional programme below forms part of the Community Consultation process
for the site to inform the Hesleden Community of known activities in advance.
The programme will be updated and reissued as and when work activities are
known.
Please
note the programme is subject to change and based on current site knowledge and
will also be dependent on weather conditions.
The
site has 24 hour security and is monitored by CCTV linked to a central system.
Week
Commencing
|
Programmed Work
Activity
|
17th
July 2017
|
Site
compound Set up, Perimeter fencing, Construction of screening bund.
|
24th
July 2017
|
Site
compound Set up, Perimeter fencing, Construction of screening bund, some
offsite disposal of material.
|
31st
July 2017
|
Site
compound Set up, Perimeter fencing, Construction of screening bund, some
offsite disposal of material
|
7th
August 2017
|
Construction
of access ramp to lagoons, some offsite disposal of material
|
14thAugust
2017
|
Construction
of access ramp to lagoons, some offsite disposal of material
|
21st
August 2017
|
Construction
of access ramp to lagoons, some offsite disposal of material
|
28thAugust
2017
|
Construction
of lagoons, some offsite disposal of material, some additional tree felling,
construction of protection bund along Hesleden Dene
|
4th
September
|
Construction
of lagoons, some offsite disposal of material, some additional tree felling,
construction of protection bund along Hesleden Dene
|
11th
September
|
Construction
of lagoons, some offsite disposal of material, some additional tree felling,
construction of protection bund along Hesleden Dene
|
|