Northumbrian Water has applied to the council for a temporary road closure order at Hart Crescent, Blackhall Rocks to enable them to carry out sewer replacement works next month.
The works are scheduled to begin on Monday 1 September and are estimated to take three weeks to complete. The Order is published below for further information but to be clear, the road is to be closed from the junction with the A1086 at Cod on the Rocks to the junction with Bevin Grove:
Hart Crescent, Blackhall Colliery
Temporary
Road Closure Order
An Order is being made under the
provisions of Section 14(1) of the Road Traffic Regulation Act 1984 the effect
of which will be to close to vehicular traffic from Monday 1 September 2014 a
70 metre length of Hart Crescent that extends south westwards from its junction
with A1086 Coast Road, Blackhall Colliery.
The closure is necessary to
enable new sewer installation
works to be undertaken which will probably take some 3 weeks to complete to be carried out to that
length of road.